Cody Pools: 101 E. Old Settlers Blvd., Ste. 100, Round Rock
Type of work: renovation/alteration
Estimated cost: $200,000
Timeline: April 4-May 31
Scope of work: project consists of the demolition and finish-out of an existing demised tenant suite; suite occupancy classification and use group remains unchanged by this scope of work
The Narrows Big House: 300 CR 137, Hutto
Type of work: new construction
Estimated cost: $250,000
Timeline: June 1, 2022-June 1, 2024
Scope of work: one-story leasing facility/clubhouse for 244 units
Pflugerville Medical Complex: 17709 Colorado Sand Drive, Pflugerville
Type of work: new construction
Estimated cost: $3 million
Timeline: Nov. 1, 2022-Aug. 31, 2023
Scope of work: construct a two-story shell medical office building and associated parking and sitework; building will contain one elevator and two stairs
Lakeside WCIDA2 Speidel Trail: Speidel Drive, Pflugerville
Type of work: new construction
Estimated cost: $50,000
Timeline: Oct. 15, 2022-Jan. 15, 2023
Scope of work: construction of a 6-foot-wide pedestrian trail
Aura Avery Centre II: 3350 N. A.W. Grimes Blvd., Round Rock
Type of work: new construction
Estimated cost: $999,999
Timeline: May 22, 2022-Nov. 22, 2023
Scope of work: three-story garden-style wood frame apartment buildings, 11 carports, three detached garages, one trash compactor and one dog wash