The Seasons at Chandlers Creek - Office 600: 2200 N. A.W. Grimes Blvd., Round Rock
Type of work: new construction
Timeline: March 28-July 1
Estimated cost: $500,000
Scope of work: office condo
Miss A: 4401 N. I-35, Ste. 423, Round Rock
Type of work: renovation/alteration
Timeline: April 15-Sept. 30
Estimated cost: $100,000
Scope of work: Interior remodel, electrical, demolition and new flooring
Planet Fitness: 200 Palm Valley Blvd., Round Rock
Type of work: renovation/alteration
Timeline: March 1-April 1
Estimated cost: $500,000
Scope of work: interior alteration of existing workout facility
Austin Achieve Pflugerville Primary School: Pfennig Lane adjacent to 1501 FM 685
Type of work: new construction
Timeline: Aug. 20, 2022-Aug. 1, 2023
Estimated cost: $18 million
Scope of work: new elementary school on a newly developed site
Old Navy: 2710D Parker Road, Round Rock
Type of work: renovation/alteration
Timeline: July 10-29
Estimated cost: $3 million
Scope of work: replace existing cash wrap, reconfigure and replace wall cabinets, relamp lighting fixtures, new lighting, new flooring, update restroom accessories, outlets added and power washing