Autism Learning Partners: 1208 N I-35, Ste. 100, Round Rock
Type of work: additions to existing building
Timeline: Nov. 30-Jan. 15
Estimated cost: $250,000
Scope of work: interior alteration to an existing tenant space in an existing one-story retail building, including demo, new metal stud-framed walls and updated restroom fixtures
The Depot Townhomes: 115 E. Bagdad Ave., Round Rock
Type of work: new construction
Timeline: Dec. 16, 2021-Dec. 5, 2022
Estimated cost: $2,500,000
Scope of work: construction of townhomes consisting of buildings, grading, sidewalks, private driveways, wastewater systems, storm sewer systems, paving, signage and retaining walls
East Bagdad Avenue public improvements: East Bagdad Avenue, Round Rock
Type of work: renovation/alteration
Timeline: Dec. 6-June 6
Estimated cost: $1,400,000
Scope of work: improvements to existing East Bagdad Avenue consisting of asphalt paving, curb and gutter, pavement marking signage, driveway reconstruction, retaining wall, wastewater system, water system, storm sewer, landscaping and sidewalks
Tropical Smoothie Cafe: 2100 Autumn Slate Drive, Ste. 100, Pflugerville
Type of work: renovation/alteration
Timeline: Dec. 1-Feb 28
Estimated cost: $150,000
Scope of work: interior finish-out for a new commercial restaurant in an existing shell building
Livano multifamily housing: 3001 E. Pecan St., Pflugerville
Type of work: new construction
Timeline: Jan. 10, 2022-June 26, 2024
Estimated cost: $150,000
Scope of work: new multifamily housing development of 10 unique building types and 463 dwelling units with multiple parking options, dedicated and integrated amenity facilities, and pocket parks designed in a modern Texas farmhouse theme