Wondering what renovations and new construction are underway or set to begin soon in Round Rock and Pflugerville? The following commercial projects have been filed through the Texas Department of Licensing and Regulation. All information, including cost and timeline, is subject to change.

1. Emerson Automation Solutions courtyard infill: 1100 W Louis Henna Blvd. W., Round Rock

Type of work: additions to existing building

Timeline: Jan. 2-Sept. 29

Estimated cost: $2.3 million


Scope of work: new building addition (infill) between two existing buildings; 50% of the project is an amenity building area, and 50% is the exterior courtyard

2. Cody Pools: 101 E Old Settlers Blvd., Round Rock

Type of work: renovation/alteration

Timeline: Dec. 9-March 3


Estimated cost: $675,000

Scope of work: demolition and finish-out of an existing demised tenant suite

3. Grand Avenue Plaza: 114 Grand Avenue Parkway, Pflugerville

Type of work: new construction


Timeline: March 1-May 1, 2023

Estimated cost: $1.5 million

Scope of work: new construction of two retail buildings' shell

4. Target: 121 Louis Henna Blvd., Round Rock


Type of work: renovation/alteration

Timeline: April 25-Aug. 22

Estimated cost: $2.53 million

Scope of work: modify office layout and convert office space into stock at front of store for order pickup efforts; add optical to office space; convert food service to Starbucks; modify guest service, fitting rooms, and restrooms; replace check lanes; update finishes


5. Atmos Energy office renovation: 3110 N. I-35 Frontage Road, Round Rock

Type of work: renovation/alteration

Timeline: Jan. 3-Sept. 30

Estimated cost: $1.4 million

Scope of work: office renovation of existing office building gutting the interior with new finish-out, adding new exterior windows and openings, new break room, covered patio, new mechanical system, modified plumbing and electrical systems to support new finish-out