Avery Nelson Parkway: 4000 College Park Drive, Round Rock
Type of work: new construction
Timeline: Jan. 1-June 30
Estimated cost: $100,000
Scope of work: construction of sidewalks and pedestrian ramps associated with the Avery Nelson Parkway roadway extension project
Brushy Creek Elementary School: 3800 Stonebridge Drive, Round Rock
Type of work: renovation/alteration
Timeline: Jan. 10-Dec. 1, 2022
Estimated cost: $8.4 million
Scope of work: 24,000-square-foot classroom addition, renovation to existing gym, cafeteria and classroom ceiling replacement
Round Rock High School: 201 Deep Wood Drive, Round Rock
Type of work: renovation/alteration
Timeline: Dec. 1-Aug. 1, 2022
Estimated cost: $800,000
Scope of work: new canopies and sidewalks
Emerson Automation Solutions Nex-Gen 2W: 1100 W. Louis Henna Blvd. W., Round Rock
Type of work: renovation/alteration
Timeline: Start date is Nov. 1-March 28
Estimated cost: $3.2 million
Scope of work: interior build-out of existing shell space on level 2W of west building 1 for new office workspace
7-Eleven renovation: 15829 I-35, Pflugerville
Type of work: renovation/alteration
Timeline: Feb. 21-April 4
Estimated cost: $440,000
Scope of work: remodel of existing convenience store to include equipment modifications, updates and new propane tank with new slab