685 Shell Gas Station—618 FM 685, Pflugerville
Type of work: renovation/alteration
Timeline: start date is Sept. 1, completion date is March 1
Estimated cost: $120,000
Scope of work: remodel and add 588 square feet to existing 2,480-square-foot one-story convenience store
Frontera Crossing Suite 301—101 W. Louis Henna Blvd., Ste. 301, Round Rock
Type of work: renovation/alteration
Timeline: start date is Oct. 18, completion date is March 31
Estimated cost: $300,000
Scope of work: interior renovation of existing tenant space
Cedar Ridge HS CTE renovation—2801 Gattis School Road, Round Rock
Type of work: renovation/alteration
Timeline: start date is Nov. 1, completion date is June 30
Estimated cost: $1 million
Scope of work: scope consists of the demolition and renovation of the flooring in the existing culinary kitchen and dressing area; in addition, we will be converting the existing home arts kitchen into a second culinary kitchen with a bistro
Round Rock MOB Ph 2, Medical Oaks Plaza—2410 Round Rock Ave., Round Rock
Type of work: additions to existing building
Timeline: start date is Jan. 3, completion date is Dec. 30
Estimated cost: $8.3 million
Scope of work: core and shell construction for a medical office building
Coast Spa Lifestyles—2701-B Parker Drive, Round Rock
Type of work: renovation/alteration
Timeline: start date is Oct. 1, completion date is Dec. 31
Estimated cost: $500,000
Scope of work: new mixed-use retail/apartment building