Pflugerville and Hutto have several major transportation projects planned and in progress to reconstruct streets and address gaps in the transportation network. Read more about the projects below.

Pflugerville

Ongoing projects

Colorado Sand Drive from Copper Mine Drive to Lone Star Ranch Boulevard

Project: Construction of 0.53 miles of four-lane paved roadway to fill the gap on Colorado Sand Drive between Copper Mine Drive and Lone Star Ranch Boulevard, including a roundabout


Update: Construction is ongoing and will wrap up this year.
  • Timeline: 2019-2025
  • Cost: $9.9 million for total project
  • Funding source: 2023 certificate of obligation bonds, 2020 general obligation bonds and roadway impact fees
Kelly Lane Phase 2 from Falcon Point to Moorlynch Avenue

Project: Widening Kelly Lane from two to four lanes from Falcon Pointe Drive to east of Moorlynch Avenue, including a roundabout at Vilamoura Street

Update: Final construction activities will continue through September.
  • Timeline: 2019-2025
  • Cost: $27.6 million for total project
  • Funding source: 2020 certificate of obligation bonds, 2020 general obligation bonds and roadway impact fees
Street Reconstruction Package 1B

Project: The neighborhood street reconstruction project will rehabilitate 18 neighborhood streets in the Saxony and Willow Creek Section One subdivisions.


Update: Construction started in July and will last approximately six months.
  • Timeline: 2023-2025
  • Cost: $5.9 million
  • Funding source: 2023 certificate of obligation bonds, 2020 general obligation bonds


Future construction

Kelly Lane Phase 3

Project: The Kelly Lane Phase 3 project will expand the roadway to a four-lane configuration with a center median and integrate four roundabout intersections from Moorlynch Avenue to Weiss Lane.


Update: The project has entered the final phases of design, and construction will begin with utility relocation.
  • Timeline: 2020-2028
  • Cost: $28.7 million
  • Funding source: 2022 and 2023 general obligation bonds and roadway impact fees
Residents can stay up to date on Pflugerville traffic advisories here.

Hutto

Ongoing projects

FM 1660 at Limmer Loop


Project: Construction of turn lanes and signal improvements at the intersection of FM 1660 North and Limmer Loop

Update: The road is under construction with an estimated completion of late 2025. Final paving and striping are expected soon.
  • Timeline: 2023-2025
  • Cost: $7,884,001
  • Funding Source: 2022 general obligation bonds
FM 3349 Overpass

Project: Williamson County is building an overpass welcome sign over FM 3349.

Update: The overpass sign is under construction with an estimated completion by the end of the year.
  • Timeline: 2025
  • Cost: $95,000 budgeted
  • Funding Source: Transportation Improvement Fund
Future construction


Exchange Boulevard reconstruction

Project: Improvements to Exchange Boulevard at the intersection with Live Oak Street

Update: Design is 90% complete. Work continues as right-of-way details are finalized.
  • Timeline: 2025-2026
  • Cost: $4.4 million budgeted
  • Funding Source: 2022 general obligation bonds
FM 1660 South at Hwy. 79

Project: Construction of the turn lanes and signal improvements at the intersection of FM 1660 South and Hwy. 79, and the intersection of FM 1660 South and Front Street

Update: Now moving forward with TxDOT and Union Pacific Railroad coordination. TxDOT design of the signal at Front Street is now complete.
  • Timeline: 2023-2027
  • Cost: $4,453,574 budgeted
  • Funding Source: 2022 general obligation bonds
Hutto residents can stay up to date on road closures and other advisories here.