Curious about which new businesses, restaurants and facilities are coming soon or currently underway in your backyard and beyond? Our commercial permit roundup helps identify what is being built in your community. The following commercial permits have been filed recently in Pflugerville and Hutto under the Texas Department of Licensing and Regulation. All information, including cost and timeline, is subject to change.

Habitat for Humanity ReStore: 21315 CR138, Pflugerville

Type of work: new construction

Estimated cost: $10 million

Timeline: April 1, 2023-May 31, 2024


Scope of work: This is a phased project. The total project will consist of a ground-up retail store with a storage area and support spaces.

Hotworx Studio: 208 E. Wells Branch Parkway, Ste. 203, Pflugerville

Type of work: renovation/alteration

Estimated cost: $180,000


Timeline: Nov. 21, 2022-Jan. 31, 2023

Scope of work: gym/sauna interior build-out

Pizza Shop: 1300 W. Pflugerville Parkway, Ste. 340, Pflugerville

Type of work: additions to existing building


Estimated cost: $75,000

Timeline: Sept. 12-Dec. 12

Scope of work: 1,000-square-foot space in an existing retail center

Sports Bar: 1300 W. Pflugerville Parkway, Ste. 300, Pflugerville


Type of work: renovation/alteration

Estimated cost: $120,000

Timeline: Sept. 19-Jan. 16

Scope of work: 2,715-square-foot tenant finish-out of new sports bar in an existing retail center


ADC Pflugerville Clinic: 1512 Stone Hill Drive, Ste. 100, Pflugerville

Type of work: renovation/alteration

Estimated cost: $1.75 million

Timeline: Nov. 14, 2022-July 28, 2023

Scope of work: renovation of existing clothing store to an outpatient clinic with exam rooms and X-ray



Casa Jalisco: 125 Co-Op Blvd., Hutto

Type of work: renovation/alteration

Estimated cost: $900,000

Timeline: Oct. 31, 2022-March 31, 2023

Scope of work: new interior finish-out

Nail Time Bar: 4909 Gattis School Road, Hutto

Type of work: renovation/alteration

Estimated cost: $400,000

Timeline: Sept. 14, 2022-Feb. 17, 2023

Scope of work: interior tenant finish-out

KTM Smokes: 133 E. Front St., Ste. 400, Hutto

Type of work: new construction

Estimated cost: $110,000

Timeline: Oct. 18, 2022-Jan. 18, 2023

Scope of work: interior finish-out for retail smoke shop

Vista Windows & Doors: 100 TK Industrial Blvd., Ste. 104, Hutto

Type of work: new construction

Estimated cost: $285,000

Timeline: Sept. 26-Dec. 30

Scope of work: The project is to construct 2,355 square feet of new air-conditioned office space inside a single-story 28,125-square-foot building.

Titan Hutto VII: Innovation Boulevard, Hutto

Type of work: new construction

Estimated cost: $20 million

Timeline: Dec. 14, 2022-Dec. 14, 2023

Scope of work: this project involves the design and construction of a new, one-story, 212,840-square-foot tilt-up concrete building located in Hutto. It is speculated that the building will service multiple future tenants using warehouse and office spaces.