Pflugerville Medical Complex: 17709 Colorado Sand Drive, Pflugerville
Type of work: new construction
Estimated cost: $3,000,000
Timeline: Nov. 1, 2022-Aug. 31, 2023
Scope of work: construct a two-story shell medical office building with associated parking and site work; building will contain one elevator and two sets of stairs
Lakeside Water Control & Improvement District No. A2 Speidel Trail: Speidel Drive, Pflugerville
Type of work: new construction
Estimated cost: $50,000
Timeline: Oct. 15, 2022-Jan. 15, 2023
Scope of work: construction of a 6-foot pedestrian trail
Aura Avery Centre II: 3350 N. A.W. Grimes Blvd., Round Rock
Type of work: new construction
Estimated cost: $999,999
Timeline: May 22, 2022-Nov. 22, 2023
Scope of work: three-story, garden-style wood frame apartment buildings; 11 carports; three detached garages; one trash compactor; and one dog wash
Hutto Vape Shop: 525 Chris Kelly Blvd., Ste. 400, Hutto
Type of work: renovation/alteration
Estimated cost: $90,000
Timeline: March 25-May 25
Scope of work: finish out of a 100-square-foot space in an existing retail center
McAlister’s Deli: Chris Kelley Blvd., Hutto
Type of work: new construction
Estimated cost: $1,300,000
Timeline: March 28-Aug. 27
Scope of work: freestanding McAlister’s Deli restaurant