Highlights of Hutto, Building A: 531 Ed Schmidt Blvd., Hutto
Type of work: renovation/alteration
Timeline: March 1-May 2
Estimated cost: $100,000
Scope of work: existing one-story, approximately 1,133 square feet to be finished-out by tenants under separate permits; work includes frame interior partition walls for an accessible toilet room, install door and frame, gypsum board and grid ceiling.
Dance Spot: 4400 Sam Bass Road, Round Rock
Type of work: new construction
Timeline: Jan. 31-July 31
Estimated cost: $2.16 million
Scope of work: new dance studio
Mobotrex: 15825 Impact Way, Bldg. 1, Ste. 100, Pflugerville
Type of work: new construction
Timeline: May 10-Aug. 4
Estimated cost: $1.5 million
Scope of work: Factory creation
S. Mays Gateway Enhancements: South Mays St., Round Rock
Type of work: renovation/alteration
Timeline: March 18-Oct. 19
Estimated cost: $1.65 million
Scope of work: construction of masonry walls, columns, screens and signage; additional concrete sidewalks; and associated landscape and irrigation improvements along South Mays Street from Logan Street to Hesters Crossing Road
Emory Crossing Amenity Center: 418 Emory Crossing Blvd., Hutto
Type of work: new construction
Timeline: Feb. 1-Nov. 30
Estimated cost: $3.3 million
Scope of work: new amenity building with two pavilions, a pool and a splash pad