5 things to know about the 'fast-approaching' MoPac opening

Level-up paving on the northbound side of MoPac is nearly complete to prepare the roadway for the final layer of pavement in mid-September.

Level-up paving on the northbound side of MoPac is nearly complete to prepare the roadway for the final layer of pavement in mid-September.

The full opening of the MoPac express lanes is still a couple months out, but the Central Texas toll agency anticipates opening the entire northbound lane later this month.

Here are 5 things to know about the opening from Wednesday’s Central Texas Regional Mobility Authority board meeting:

1. The rest of the northbound lane will likely open in late September
The MoPac contractor, CH2M—which announced in January it would subcontract the remainder of the project to Lane Construction, citing a $66 million loss on the project—plans to have the northbound lane finished in late September, according to Steve Pustelnyk, director of community relations for the Mobility Authority, which is overseeing the MoPac Improvement Project between Parmer Lane and Cesar Chavez Street.

Starting next week, workers will be laying the final layer of pavement to the northbound lane. The section north of RM 2222 opened last October.

Although targeted opening dates have changed this year, the agency is preparing to launch another media campaign this month.



2. On the southbound side, that lane will not be ready until early November
Although the opening is “fast-approaching at this point,” the southbound lane might not open until early November, Pustelnyk said.

Crews are still milling existing pavement on the southbound side and will soon start level-up paving that will prepare the roadway for the final layer of pavement.

3. The underpasses, which are pretty much complete, are not Harvey-proof
Although the agency reported no flooding during Hurricane Harvey, if the Austin region experiences Harvey-level rains of several inches per hour, those underpasses could flood.

“The underpasses handled the hurricane event very well,” Pustelnyk said. “The good news with these underpasses is that they are at a higher elevation than where they drain to. Other than a rain that exceeds the ability of the inlets and the pipes that handle it, it will drain well.”

The Mobility Authority has also installed a flood detection system that would automatically notify the agency of any standing water so it could close the underpasses, which drain to Johnson Creek, Pustelnyk said.

“I feel personally much better about the drainage than I did maybe going in,” Mobility Authority Executive Director Mike Heiligenstein said. “I now have the confidence that they can handle it.”

4. Tolls could be in the $2 range
Currently, the peak toll on the open northbound section is around $0.75, but that is because that section is the least traveled portion of the MoPac project, Pustelnyk said.

Agency research indicates the total cost of the toll for driving the entire length of the express lane in one direction could be in the $2 range, he said. Once the lanes open, the Mobility Authority will use sensors installed along the corridor to monitor traffic flow and traffic counts.

The tolling system has already been installed, and the agency is testing it.

5. Remaining landscaping work could be pulled out of the project under a separate contract
In May, the agency already pulled some work from the MoPac project to manage under separate contracts for time and cost savings. Remaining landscaping work could also be completed in a similar fashion, the board discussed Wednesday.

“A big part of [the project] is making sure those underpasses are reconnecting the east and west sides of MoPac in a way that is aesthetically pleasing, good for pedestrians and bicycles and is good for the community,” Heiligenstein said. “That’s going to be a definite upgrade. These elements are really crucial for, I think, a successful project at the end of the day."

Disclosure: Amy Ellsworth, general manager for Community Impact Newspaper’s Round Rock-Pflugerville-Hutto edition, was appointed in February to the Central Texas Regional Mobility Authority board of directors, serving a two-year term through Jan. 31, 2019.
By Amy Denney

Managing Editor, Austin metro

Amy has worked for Community Impact Newspaper since September 2010, serving as reporter and later senior editor for the Northwest Austin edition as well as covering transportation in the Austin metro. She is now managing editor for the 10 publications in the Central Texas area from Georgetown to New Braunfels.



MOST RECENT

Brandon Cardwell, the district's executive director of facilities and construction, addressed the PfISD board during an Oct. 21 meeting. (Brian Rash/Community Impact Newspaper)
Bohls Middle School within PfISD slated for late December completion

Brandon Cardwell, the district's executive director of facilities and construction, said during the district's Oct. 21 board meeting that much work is still needed on the campus, but he is encouraged by the pace at which crews are operating.

Cumby Group is planning development for three adjacent multifamily projects on Manor Road in East Austin, including The Emma apartments. (Courtesy Cumby Group)
3 years in, Austin is falling behind on goals in affordable housing plan

From 2018-20, the city only reached 12% of its 10-year goal to build thousands of new homes and rental units.

Taco Palenque is now open as drive-thru only in Round Rock. (Brooke Sjoberg/Community Impact Newspaper)
CI NATION ROUNDUP: Taco Palenque opens in Round Rock; Plano ISD considering two draft calendars for 2022-23 school year and more top news

Take a look at the top five trending stories across all of Community Impact Newspaper’s coverage areas as of Oct. 21.

The Austin Transit Partnership is exploring above- and below-ground options for a transit center at the East Riverside Drive and South Pleasant Valley intersection. (Courtesy Austin Transit Partnership)
Project Connect plans to explore above-, below-ground options for East Riverside/Pleasant Valley Transit Center

After hosting a community design workshop, the group overseeing Project Connect designs is moving forward with options for both an underground and above-ground station at the intersection.

A calculator created by the Rocky Mountain Institute looks at the environmental impact of TxDOT's proposed designs for I-35 in Central Austin, one of the most congested roadways in the country. (Benton Graham/Community Impact Newspaper)
Nonprofit's tool says TxDOT I-35 expansion proposals would have profound environmental consequences

The tool says that the proposal would create between 255 and 382 million additional vehicle miles traveled per year.

Photo of the Travis County administration building and sign
Travis County hears update on process to reassess master plan for aging correctional facilities

The process comes after county commissioners opted to pause all activities of the master plan over the summer.

A sold lot in the Cortaro development in Dripping Springs is under construction. (Maggie Quinlan/Community Impact Newspaper)
Housing market shows signs of stabilizing, but median prices in Southwest Austin area remain high

Hays County is growing fast and selling houses for more and more money, though the number of sales is down year over year, data show.

Rodeo stock image
Inaugural Williamson County Fair and Rodeo ready to open gates Oct. 21 after coronavirus delay

After the inaugural Williamson County Fair and Rodeo was postponed in 2020, county and fair officials said they are excited to kick off the agricultural celebration.

Renderings of the conceptual tower were shown depicting a roughly 100-foot tower, but the intent is to build a smaller tower. A total of $2.43 million was given as an estimated cost for a 100-foot gravity tower, but presenters said the cost would scale down with a smaller tower. (Courtesy city of Frisco)
CI NATION ROUNDUP: Early concept for Frisco’s Northwest Community Park includes biking tower for ‘gravity riding’; Perky Beans Cafe now open in Leander, and more top news

Take a look at the top five trending stories across all of Community Impact Newspaper’s coverage areas as of Oct. 20.

The future of West Austin's Lions Municipal Golf Course depends on the outcome of a city rezoning process and its landowner, The University of Texas. (Ben Thompson/Community Impact Newspaper)
As Austin's rezoning of UT lands continues, time could be running out for Muny course preservation

The historic golf course's future remains unclear amid a city zoning process that could ease the land's redevelopment.

Austin Cultural Arts Division staff provided an update on several funding opportunities for the creative sector Oct. 18. (Screenshot via city of Austin)
Austin's arts community could be in line for millions more in relief dollars this year

Additional relief for artists may be available in the coming months, while a broader review of the city's cultural funding opportunities continues.