Work to add extended entrance/exit lanes on Loop 360 to improve intersections with Walsh Tarlton Lane, the Barton Creek Square Mall entrance, Loop 1 and the intersection just south of Loop 1 was completed in December. A left-turn lane was also added on the Loop 1 frontage road at Loop 360 to create a triple left-turn lane from northbound Loop 1 to northbound Loop 360. Although the project is now in its final configuration, the Texas Department of Transportation still must finish paving, which will be completed this spring.

Timeline: February 2016-December 2016
Cost: $6.44 million
Funding sources: TxDOT