Transportation Updates Lake Travis | Westlake1. Traffic signal at Lohmans Crossing Road and Lohmans Spur


The city of Lakeway will add a traffic signal at the intersection of Lohmans Crossing Road and Lohmans Spur. City staff was authorized by Lakeway City Council on Feb. 16 to advertise and receive bids for the project.


City Manager Steve Jones said that although few collisions have been recorded at this intersection, more accidents are expected as traffic increases. He said a signal should make Lohmans Spur easier to use, and a traffic study showed a signal was warranted at the intersection.


Timeline: April (bids)-August (completion)
Cost:  $246,500-$275,000
Funding sources: city of Lakeway Capital Reserve Fund



2. Loop 360 entrance/exit lanes


The Texas Department of Transportation will add extended entrance and exit lanes on Loop 360 to improve intersections with Walsh Tarlton Lane, the Barton Creek Square Mall entrance, MoPac and the intersection just south of MoPac in Austin. A left-turn lane will also be added on the northbound frontage road of MoPac at Loop 360.


Timeline: February 2016-spring 2017
Cost: $6.44 million
Funding sources: TxDOT



3. MoPac toll lanes


Upon completion the highway will have one new lane in each direction from Parmer Lane to Cesar Chavez Street that will be tolled. Current construction includes bridge widening, building sound walls, installing conduit and cables to support the toll-collection and intelligent transportation systems, and completing the relocation of temporary ramps. The timeline was delayed from a fall 2015 completion to late 2016.


Timeline: late 2013-late 2016
Cost: $204 million
Funding sources: federal and state funds



4. 5. RR 620 intersections


Transportation Updates Lake Travis | Westlake Traffic signal installation[/caption]

TxDOT will add a traffic signal on RR 620 at Dave Drive and a traffic signal at Oak Grove Boulevard in northern Lakeway before the 2016-17 school year begins in the fall, said Kelli Reyna, TxDOT Austin District public information officer.


She said the agency routinely studies major intersections to see if signals would be beneficial and determined that the intersections warrant a traffic signal.


Timeline: unknown-fall 2016
Cost: $150,000 for each traffic signal totaling $300,000
Funding sources: TxDOT



6. Flint Rock Road


Transportation Updates Lake Travis | Westlake Roadway widening[/caption]

Approximately 2 miles of the two-lane Flint Rock Road—between RR 620 at Lakeway Regional Medical Center and Serene Hills Drive—will be widened with a buffer and asphalt shoulder added. The project is expected to take 15 months to complete depending on the weather, and Travis County will manage the construction phase performed by Smith Contracting Co. Construction began in the fall with the erection of signage and erosion protection. Early segments of the project include brush clearing and the construction of temporary travel lanes for traffic control.


Road paving of the project began in January and is expected to continue sporadically throughout the project until late 2016.


Timeline: October 2015-late 2016
Cost: $9.2 million total with 47 percent funded by the city of Lakeway and 53 percent funded by Travis County
Funding sources: city of Lakeway, Travis County