Comal County jail, sheriff’s office renovation project moves forward

0

Construction on the new Comal County Jail and Sheriff’s Office renovation are progressing, County Engineer Tom Hornseth told the Comal County Commissioners Court Thursday.

With all subcontractors in place and underground work complete, the first wall and slab are expected to be poured within the next two weeks. Steel structures will directly follow pre-construction.

“It’s going to be real fascinating once the heavy lifting starts, and it will probably go pretty quick,” Hornseth said.

Although the project is about two weeks behind schedule, Hornseth told commissioners construction crews are working to make up the time.

“This is an extremely complex building with all the communications and plumbing that goes with it,” Hornseth said.

Comal County broke ground in November on the $76 million jail and sheriff’s office renovation project. The site is located at South Water Lane at I-35 in New Braunfels. It is slated for completion in the summer of 2020.

Share this story
COMMENT

Leave A Reply

Rachel Nelson
Rachel Nelson is editor of the New Braunfels edition of Community Impact Newspaper. She covers local business, new development, city and county government, health care, education and transportation. Rachel relocated to Central Texas from Amarillo in 2009 and is a graduate of Texas State University's School of Journalism and Mass Communication.
Back to top