Leander City Council on June 5 approved a contract with Lone Star Paving Company for roadway rehabilitation on various stretches around the city.

The $1.41 million contract will provide for the rehabilitation of 8.8 lane miles of roads, according to agenda documents.

The gist

Roadways across the city are evaluated annually to assess whether they need improvements, according to the documents.

The roads and areas selected for rehabilitation in 2025 are:
  • 1.3 lane miles on Hero Way West
  • 1.8 lane miles on Horizon Park Boulevard
  • 0.8 lane miles on Osage Drive
  • 1.9 lane miles on Leander Drive
  • 1.5 lane miles on streets in the Overlook Estates subdivision
  • 1.5 lane miles on streets in the Mason Ranch subdivision
What else?


According to the documents, the work is set to be done by Sept. 30.

In the event that the work is not done on time, the contractor will have to pay the city $1,000 per day until the project is complete.