Updated July 17 at 11:45 a.m. to include map of proposed Lohmans Spur extension in front of the to-be-built Lakeway Police Station.
Published July 14 at 5:30 a.m.
- Approximately 2 miles of Flint Rock Road—between RM 620 at Baylor Scott & White Medical Center-Lakeway and Serene Hills Drive—will be widened and an asphalt shoulder added for a total cost of $9.2 million, with Lakeway’s share being $4.2 million and the remainder attributable to Travis County. Paving was delayed due to rain and pushed back the project’s substantial completion from the end of June to early July. The asphalt layer and final striping is slated to be finished at the end of July.
October 2015-end of July 2017 (substantial completion)
An $80 million project to widen RM 620 from four lanes to a six-lane, divided road stretching from West Hwy. 71 to the Colorado River is in development. The Texas Department of Transportation is managing the project.
August 2023 bid
A $9.8 million project to construct a four-lane urban roadway with a continuous left-turn lane, storm drains and signals on Bee Caves Road is underway from just east of Redbud Trail to 1,000 feet west of Buckeye Trail.
A $13.2 million project to construct a four-lane urban roadway on Bee Caves Road with a continuous left-turn lane, storm drains and signals is underway from 1,000 feet west of Buckeye to Walsh Tarlton Lane.
Nov. 1, 2016-summer 2019
MoPac toll lanes
Work continues on the MoPac express toll lanes between Parmer Lane and Cesar Chavez Street. Major structural construction wrapped up in late May on this stretch of lanes. Through the summer, crews will be laying the final layer of pavement. The MoPac contractor previously expected to complete the project in June, but TxDOT is now anticipating the project will be finished sometime this summer.
Timeline: October 2013-summer 2017
Cost: $204 million
Funding sources: various
Lohmans Spur Road extension
This map shows the proposed extension for Lohmans Spur to accommodate the to-be-built Lakeway Police Station.[/caption]
As part of Lakeway’s May 6 bond initiative, Lohman’s Spur Road will be extended within the next year to accommodate the build-out of the city’s new police station. The project has a preliminary engineering design, but the city is reviewing cost-saving measures on the project that may change its design.
Timeline: June-December 2018
Cost: $1,000,000
Funding source: city of Lakeway
Flintridge Road water line
A Water Control & Improvement
District 10 bond project to install an 8-inch diameter pipe under Flintridge Road in West Lake Hills began in June and could be completed by mid-August.
Timeline: June-August 2017
Cost: $639,839
Funding source: WCID 10
Bridge replacement
A bridge and approach on Crumley Ranch Road at Rocky Creek will be replaced. The project is currently being finalized for construction.
Bid date: May 2019
Cost: $700,000
Funding source: TxDOT