CYCED Indoor Cycling Studio: 15500 W. Hwy. 71, Bldg. C, Ste. 140, Bee Cave
Type of work: new construction
Estimated cost: $250,000
Timeline: July 1-Sept. 30
Scope of work: new fitness studio for indoor cycling with support areas and restrooms
Freeze Frame, LLC: 15511 W. Hwy. 71, Bee Cave
Type of work: new construction
Estimated cost: $225,272
Timeline: July 1-Oct. 1
Scope of work: commercial finish-out
YogaSix: 12800 Hill Country Blvd., Ste. G-130, Bee Cave
Type of work: renovation/alteration
Estimated cost: $300,000
Timeline: June 18-Oct. 31
Scope of work: tenant improvement project; interior build-out of existing space to a hot yoga studio; work to include interior walls, ceilings, accessible restrooms, finishes, millwork, and mechanical, plumbing and electrical systems
Westlake Career Center: One Destiny Way, Westlake
Type of work: renovation/alteration
Estimated cost: $125,000
Timeline: May 30-Aug. 29
Scope of work: interior renovation
Flower Child: 3300 Bee Caves Road, West Lake Hills
Type of work: renovation/alteration
Estimated cost: $900,000
Timeline: June 1-Oct. 5
Scope of work: new restaurant in a tenant remodel space
American Bank: 3520 Bee Caves Road, West Lake Hills
Type of work: renovation/alteration
Estimated cost: $520,000
Timeline: July 18-Nov. 18
Scope of work: interior finish-out
Butterfly Christian Preschool: 3525 Bee Cave Road, West Lake Hills
Type of work: renovation/alteration
Estimated cost: $1.5 million
Timeline: May 23-Sept. 5
Scope of work: The project includes new interior finishes, a full exterior window replacement, a new on-site fire line for a new sprinkler system to serve the school and a fenced area for an 800-square-foot outdoor learning space.
Garages of Texas: 1009 N. FM 620, Bldg. 3, Ste. 316, Lakeway
Type of work: new construction
Estimated cost: $228,800
Timeline: June 6-Sept. 7
Scope of work: tenant fit-out of a private garage and mezzanine office space
Golshani Expansion: 5329 Serene Hills Drive, Lakeway
Type of work: new construction
Estimated cost: $215,687
Timeline: May 23-Aug. 22
Scope of work: tenant finish-out
Lake Travis Surgery Center: 6 Lakeway Centre Court, Lakeway
Type of work: new construction
Estimated cost: $2.5 million
Timeline: March 1-Nov. 30
Scope of work: new shell building and surgery center finish-out