Crews are working to install utilities, including waterlines and storm water drainage, along Shell Road, ahead of a project to widen it from Williams Drive to Sycamore Street to four lanes.
Read an update on this project, and others in Georgetown, below.
Upcoming projects
1. Williams Drive
The city project will construct medians with turn lanes on Williams Drive from I-35 to Serenada Drive, including a shared-use path on the north side of Williams Drive, a new waterline, and street lighting from DB Wood Road to Jim Hogg Road and Serenada Drive to I-35.
- Update: The project’s design is complete, and officials anticipate it to go out to bid in late April.
- Timeline: 2023-27
- Cost: $18.6 million
- Funding sources: city of Georgetown, traffic impact fees, federal grants, tax increment financing
2. SE Inner Loop
A 2.91-mile stretch of SE Inner Loop will be widened to a four-lane, divided road from Hwy. 29 to FM 1460. A shared-use path for pedestrians and bicycles will be added on one side.
- Update: The city is in the process of acquiring the right-of-way needed for the project. Design is complete and officials anticipate it to go out to bid in July.
- Timeline: 2022-28
- Cost: $70.6 million
- Funding sources: city of Georgetown, Georgetown Transportation Enhancement Corporation
3. Hwy. 29 West
The Texas Department of Transportation will construct additional travel lanes, lengthen turn lanes and improve traffic signals on Hwy. 29 from Wolf Ranch Parkway to I-35 as well as add shared-use paths.
- Update: TxDOT is expected to begin construction in September.
- Timeline: 2023-27
- Cost: $12.31 million
- Funding source: Georgetown Transportation Enhancement Corporation
4. Austin Avenue pedestrian bridges
This project will include construction of two pedestrian and bicycle bridges crossing the San Gabriel River, east of the existing Austin Avenue vehicular bridges.
- Update: The revised design is tentatively scheduled to be complete in July 2027.
- Timeline: 2023-TBD
- Cost: $21 million
- Funding sources: city of Georgetown, developer fees
5. Shell Road
The city will widen Shell Road from Williams Drive to Sycamore Street to four lanes with a raised median, shared-use path, and left- and right-turn lanes.
- Update: As of March, crews were working on utility installation for waterlines and storm water, and officials anticipate project completion in December 2027.
- Timeline: 2022-27
- Cost: $18.17 million
- Funding source: city of Georgetown
Ongoing projects
6. Rockride Lane
This work will upgrade Rockride Lane to a two-lane collector roadway with a continuous center left-turn lane and a 10-foot-wide shared-use path along one side from SE Inner Loop to Sam Houston Avenue.
- Update: The city expects substantial construction to be complete by the end of September.
- Timeline: 2022-26
- Cost: $12 million
- Funding source: city of Georgetown
7. DB Wood Road Phase 1
The project adds four 12-foot wide lanes, a center turn lane and a 10-foot shared-use path from Hwy. 29 to Oak Ridge Road.
- Update: All roads will be open for traffic in May, with substantial completion planned for July.
- Timeline: 2023-26
- Cost: $29.6 million
- Funding source: city of Georgetown