Domino’s: 1890 Crystal Falls Parkway, Leander
Type of work: renovation/alteration
Estimated cost: $225,000
Timeline: Aug. 22-Nov. 25
Scope of work: interior renovation of a new tenant suite for a retail store selling food and beverages
Texas Humane Heroes-Leander North Campus: 10930 E. Crystal Falls Parkway, Leander
Type of work: new construction
Estimated cost: $7 million
Timeline: Dec. 30-Sept. 6
Scope of work: new building and site work
Scooter’s Coffee: 3651 N. Hwy. 183, Leander
Type of work: new construction
Estimated cost: $350,000
Timeline: Nov. 28, 2022-March 6, 2023
Scope of work: new building kiosk with drive-thru service
Swadeshi Plaza Retail Shell Building 1: 183A Frontage Road, Leander
Type of work: new construction
Estimated cost: $600,000
Timeline: Aug. 31-Nov. 30
Scope of work: new construction of a retail shell building
Unleashed Unlimited Training and Boarding Facility: 1410 Live Oak Road, Leander
Type of work: new construction
Estimated cost: $1.3 million
Timeline: Nov. 1, 2022-May 1, 2023
Scope of work: Unleashed Unlimited is a dog training and boarding facility located on Live Oak Road. This project consists of a one-story above-grade structure.
Nervous Charlie’s: 410 W. Whitestone Blvd., Bldg. 3, Ste. 300, Cedar Park
Type of work: renovation/alteration
Estimated cost: $320,000
Timeline: Nov. 1, 2022-Feb. 24, 2023
Scope of work: fully-sprinklered, restaurant fit-out
Cedar Park Library: 209 S. Bell Blvd., Cedar Park
Type of work: new construction
Estimated cost: $27 million
Timeline: Nov. 1, 2022-May 31, 2024
Scope of work: Cedar Park Library is a new-construction, 47,000-square-foot, two-story library facility for the city of Cedar Park that will be a primary anchor in the city’s Bell District
Austin Sports Medicine: 1515 Medical Parkway, Bldg. 3, Ste. 100, Cedar Park
Type of work: renovation/alteration
Estimated cost: $400,000
Timeline: Oct. 17, 2022-Jan. 16, 2023
Scope of work: first generation interior finish-out
Diesel Barbershop-New Hope: 1320 Ronald Reagan Blvd., Ste. 209, Cedar Park
Type of work: new construction
Estimated cost: $180,000
Timeline: Oct. 1-Dec. 15
Scope of work: tenant upfit to a newly constructed center for the purpose of operating a barbershop
Copeland Office Building: 800 S. Bell Blvd., Cedar Park
Type of work: new construction
Estimated cost: $3 million
Timeline: March 1, 2023-March 1, 2024
Scope of work: new office building