The details
The contract amendment for design services with Austin-based Huitt-Zollars, at a cost of $59,600, came after three project issues were recently identified:
- The need for a tricolored bat survey
- A requirement from the Texas Historical Commission to use modern lighting fixtures instead of matching “old-style” light fixtures located throughout downtown Bastrop
- The importance of evaluating the Old Iron Bridge for needed structural modifications to accommodate the new lighting system
“[TCEQ] notified Huitt-Zollars that a tree survey of the area would be required because the tricolored bat has been identified to use trees to nest and that the preliminary assessment indicated would be impacted by the proposed project,” Elizabeth Wick, a project manager with the city of Bastrop, said in a staff report document.
Some background
The city hosted a kickoff event for the $10.1 million project July 26.
The project—to be completed by Dripping Springs-based Jay-Reese Contractors—will feature several improvements in addition to the decorative lighting, including:
- Adding a concrete deck
- Adding steel truss components
- Installing railing
The Old Iron Bridge, which closed in 2018 in response to safety concerns, is now on track to reopen in the fall of 2026.
“We’re going to get it done, and we’re going to get it done on time,” Bastrop City Manager Sylvia Carrillo-Trevino said.