Adelton is one of several projects funded by the 2021 and 2023 bond initiatives.
Read on to learn more about ongoing bond projects in the district.
How we got here
Voters in BISD passed over $500 million in bonds through two initiatives in 2021 and 2023.
These were the first bond proposals to be passed by voters in the district since 2007.
Projects included in the propositions include:
- Safety and security upgrades to existing campuses
- Land purchases and the construction of two new campuses
- Capacity expansions to existing campuses
- Improvements to athletic facilities
As of the August 2025 bond construction update presented by BISD Director of Construction and Planning Lee Raspberry, multiple projects were about halfway through completion.
Adelton Elementary School
- Schedule: June 2024-August 2024
- Scope of work: new 105,000-square-foot elementary school
- Status: 100% complete
- Schedule: January 2025-May 2026
- Scope of work: 35,500-square-foot campus expansion
- Status: 34% complete
- Schedule: December 2024-December 2025
- Scope of work: 21,000-square-foot campus additions
- Status: 45% complete
- Schedule: October 2024-December 2025
- Scope of work: 60,000-square-foot campus addition, new competition gym and fine arts facilities
- Status: 55% complete
- Schedule: October 2024-December 2025
- Scope of work: 60,000-square-foot campus addition, new competition gym and fine arts facilities
- Status: 50% complete
- Schedule: May 2025-December 2027
- Scope of work: 38,000-square-foot addition in permitting phase; new classroom wing and continued renovations
- Status: 11% complete
- Schedule: January 2025-March 2026
- Scope of work: 55,000-square-foot facility to serve police administration, maintenance, custodial, groundskeeping, warehouse and the district's print shop
- Status: 42% complete