There are several transportation updates around the Tomball and Magnolia area. Check them out below. This list is not comprehensive.
Upcoming projects
Hufsmith Road intersection improvements
Project: This will make improvements to the intersections of Hufsmith Road at Kuykendahl Road, Stuebner Airline Road and FM 2978.
Update: This project is now in the design phase for future planning and construction.
- Timeline: TBD
- Cost: $36,645
- Funding source: Harris County Precinct 3
Ongoing projects
FM 1488 widening west of Magnolia
Project: FM 1488 is being widened from two to four lanes with a continuous left-turn lane between the Waller County line and FM 1774 west of Magnolia.
Update: This project is 98% completed, according to the Texas Department of Transportation’s March 10 media update.
- Timeline: November 2020-second quarter 2026
- Cost: $35.35 million
- Funding source: state funds
FM 1488 widening through Magnolia
Project: Between FM 1774 and west of FM 149, FM 1488 is being widened from two to four lanes with a continuous left-turn lane.
Update: This project is 64% completed, according to TxDOT’s March 10 media update.