After more than two years of construction and delays, work on the first segment of the Medical Complex Road extension project is complete. Funding for the segment was originally approved by Tomball City Council in March 2014, however, since then the project has encountered numerous problems. Segment 3 construction wrapped up in late May.
“It’s been very frustrating,” Tomball City Manager George Shackelford said. “The contractor was actually very good; [but] the right of way acquisition was an issue and that delayed some things. And AT&T had some lines in the way that they knew about for three years before doing anything.”
The project is broken up into five segments. Funding for Segment 3 of the project comes from the city budget, with a $1.7 million contribution from the Tomball Economic Development Corporation.
The segment extends the road from where it dead ends at Lawrence Street near Tomball Regional Medical Center through to South Cherry Street. The 0.9-mile road cost over $6.1 million and was originally estimated to take less than a year.