Project overview
Split into four phases, the Hwy. 249 extension will provide a new route to Hwy. 105 in Grimes County. The $152 million Phase 1 was completed in April 2015 and stretches for six miles from Northpointe Boulevard to FM 2920 in Tomball. Since opening, the six-lane toll road has brought in an average of $1.5 million per month in toll fees, according to the Harris County Toll Road Authority.
[caption id="attachment_167730" align="alignright" width="220"]

The next phases of the Hwy. 249 extension are expected reach Magnolia and Navasota by 2019, connecting the areas to many Houston amenities, such as the Texas Medical Center and the Port of Houston.[/caption]
Phase 2 will be funded by HCTRA and will extend the existing tollway from FM 2920 to the county line at Spring Creek. The Montgomery County Toll Road Authority will take over for Phase 3, which will replace the current stretch of Hwy. 249 from Spring Creek to FM 149 with tolled lanes and frontage roads. The final phase—Phase 4—will be funded by TxDOT and will build a new four-lane road with two-lane, one-way frontage roads to the right of FM 1774. Phase 4 will begin near FM 149 in Pinehurst and end at Hwy. 105 in Navasota.
The nearly 30-mile stretch of road is expected to cost a total of $777 million according to plans from engineering firms Halff Associates and Binkley & Barfield, Inc. Phases 2, 3 and 4 will be tolled on mainlanes, entrances and exits.
Magnolia City Administrator Paul Mendes said the extension of Hwy. 249 through Magnolia will help to alleviate traffic along FM 1774 in the city, which often becomes congested in the mornings and afternoons. The project will also open the area up by providing an alternate route to FM 1774, he said.
“With [the extension,] it’ll give you a high-speed approach into the city area, and it will relieve the traffic and give [drivers] access to [the area],” Mendes said. “There are so many large parcels of land out here that are prime for development, but no one wants to develop them because of the chokehold the roads have on us. [Before] they recently widened the lanes on [FM] 1774, it was like a parking lot when everyone was going to work.”