The completion date for the project to widen FM 1774 through Magnolia—originally set for September 2014—has been delayed until early 2015 as a result of a number of subterranean utility and environmental conflicts, according to the Texas Department of Transportation.
"The combination of both utility and environmental conflicts forced the contractor to not be able to work as efficiently as they normally would on a project like this, which has caused the delay in completion," said Richard Brown, TxDOT area engineer for Montgomery County. "We do not have an exact date yet, as we are still trying to assess how much these conflicts set us back by, but we are probably looking at January or February of 2015."
Brown said the utility conflicts the project has experienced are not unusual and often expected anytime there is major construction in a small town that takes place in a narrow right of way, such as in Magnolia. The ROW in Magnolia had a number of sanitary sewer lines as well as electrical, gas and water lines that had to be worked around, he said.
On the other hand, the environmental conflicts were unforeseen, Brown said. Contractors, while constructing the road, came across five gasoline tanks from a former gas station that had been underground for decades and needed to be removed. The gas tanks were not completely empty and the remaining fuel contaminated much of the soil underground.