The completion dates for two road construction projects on Hwy. 242 have been moved to the third quarter of 2022, according to the Texas Department of Transportation.
1. A TxDOT project will construct a grade separation along Hwy. 242 from west to east of FM 1314. This is one of four projects to construct an overpass at Hwy. 242 and FM 1314. The project was 89% complete as of June 24.
Timeline: July 2018-third quarter 2022
Cost: $24.35 million