Update: The Texas Department of Transportation will handle bidding and construction, and late summer is likely the earliest start date, engineer John Bleyl said.
- Timeline: late summer-TBD
- Cost: $1.67 million
- Funding source: TxDOT
Ongoing projectsRobinson Road realignment
Project: The project will align Robinson Road across Hanna Road. The project will include realigning a portion of the Union Pacific Railroad, which is crossed by Robinson Road.
Update: As of June 10, Oak Ridge North officials said drainage ditch excavation was underway, and water line construction was expected to begin in mid-June. The Union Pacific Railroad water line bore was delayed by UPRR until late June or July due to rain and ground saturation near the tracks, Oak Ridge North officials said.
- Timeline: February-late 2024
- Cost: $7.42 million
- Funding source: city of Oak Ridge North
David Memorial Drive extension