The one-mile stretch of Woodlands Parkway between Grogan's Mill Road and East Panther Creek Drive faces serious traffic congestion and has been designated for expansion by the Woodlands Road Utility District No. 1. The project was scheduled to go to bid in fall 2011 but was delayed because of changes in the environmental assessment review process.
Plans to expand the roadway from four lanes to six lanes began in early 2009. The original environmental assessment had set project limits from I-45 to East Panther Creek, but after the portion of Woodlands Parkway from I-45 to Grogan's Mill Road was widened, a new study needed to be completed, according to the Texas Department of Transportation.
"When you change the project limits, technically you have to redo the environmental [assessment] because the project scope has changed. Everyone has their own list, and that list grows every month," said Robert Heinemen, vice president of planning for The Woodlands Development Company.
The original assessment, completed in 2010, also gave rise to concerns of inaccurate reports and the use of improper technology, said Mike Page, spokesman for the WRUD. Initially, the Federal Highway Administration (FHWA) had a one-year turn-around to review and respond to the assessment for the proposed expansion, Heinemen said. A separate firm reviewed and confirmed the findings, which has since been approved by TxDOT.