Construction on the expansion of Woodlands Parkway from Grogan's Mill Road to East Panther Creek Drive is still stalled because a new contractor for the project has yet to been chosen, according to the Texas Department of Transportation.
TxDOT officials said the project is about 82 percent complete. The westbound expansion remains incomplete.
The original construction company for the Woodlands Parkway expansion, Kingwood-based Menade Inc., was suspended from the project by TxDOT in September. Menade was taken off the project after the firm missed the construction deadline by nearly a year.
"Menade was declared in default by TxDOT after numerous meetings and letters concerning the lack of progress on the project yielded no noticeable improvements in production in February," said John Powers, assistant general manager for community services for The Woodlands Township.