1. Hwy. 242 Direct Connectors
The Hwy. 242 direct-connect projects include a northbound flyover traveling to eastbound Hwy. 242, ending at Maverick Way near Lone Star College-Montgomery, as well as a westbound flyover traveling to southbound I-45, ending south of Hwy. 242. Rick Kronenberger, project manager for PTP Transportation, said no date has been determined as to when steel beams would be placed over I-45 onto the support columns. Kronenberger said when the beams are put into place, lanes on I-45 would need to be closed. For more information about the project, visit www.sh242dc.com.
Timeline: Construction is estimated to be complete by the end of the year.
Cost: $33.9 million