With pipeline installation along Research Forest Drive nearly complete, the San Jacinto River is hoping to complete construction along Grogan's Mill Road by the end of the spring.
Eastbound lanes on Grogan's Mill Road between Research Forest Drive and South Millbend Drive are closed, except at major intersections, as crews work to install more pipeline and reinstall roadway.
"By mid-May we're out of there all together, that portion of Grogan's Mill is done," said Mark Smith, administrator for the SJRA's Groundwater Reduction Plan.
Smith said the 1-mile portion of Grogan's Mill Road between Woodlands Parkway and South Millbend Drive was initially scheduled to re-open in March, but will more likely be sometime in April.