A delay of at least a year on finishing a $6.3 million road project on South Congress Avenue from Foremost Drive to Eberhart Lane in South Austin has nearby businesses—some of which are less than a year old—anticipating the project’s completion.
On July 24, construction crews pulled barricades from closed lanes and opened all five lanes.
The Texas Department of Transportation widened the 1.35-mile stretch of Congress from three lanes to five—two in each direction and a center left-turn lane—and adding upgraded drainage facilities, new sidewalks and bicycle lanes.
[caption id="attachment_166127" align="alignright" width="460"]
Work has been in progress for more than a year on a project to widen South Congress Avenue and add safety features such as sidewalks and crosswalk updates. The project area extends from Eberhart Lane to Foremost Drive.[/caption]
“The project will enhance safety and mobility for motorists on this heavily-traveled roadway,” TxDOT area engineer Victor Vargas said.