The Georgetown Planning and Zoning Commission unanimously recommended to deny the rezoning request for a proposed data center at its Nov. 17 meeting.
Development partners Phillip Niels and Tim Keith requested to rezone approximately 28 acres located at the intersection of NE Inner Loop and East University Avenue to a planned unit development, according to city documents.
The details
The partners own the land, on which they proposed building a 68-megawatt data center known as the Inner Loop Exchange.
Georgetown's future land use plan earmarks the area for a mixed-density neighborhood, which would support different housing types and walkable streets, according to city documents.
The PUD requested would have a base zoning of commercial, with several accommodations to support the data center:
Increasing building footprint from 5,000 square feet to 290,000 square feet
Decreasing setback from 250 feet to 50 feet
Increasing rooftop coverage from 33%-35% up to 65%
Changes to landscape and fencing buffers
City staff found that the proposal does not comply with the future land use plan nor neighborhood compatibility.
What they're saying
The city received 22 written comments opposed and 0 in favor, with several residents signed up to speak at the meeting.
Residents from nearby subdivisions—including Churchill Farms, Summercrest, Riverhill and Blanco Vista—voiced objections:
Noise disruptions
Water consumption and potential strain on local electrical infrastructure
Negative impacts on property values and neighborhood appeal
Lack of retail, dining and grocery options at the site of the data center
What's next
Following the Planning and Zoning Commission's denial, the request will advance to Georgetown City Council for final action.