Citing a $66 million loss as a result of delays on the MoPac express lane project, contractor CH2M announced Tuesday it will subcontract the remainder of the project.
However, the change is not expected to affect the timeline of the new opening date for the entire project, which has been pushed back to June, according to CH2M.
“We’re pretty confident in hitting mid-June,” CH2M Project Director Craig Martell said Wednesday morning at the Central Texas Regional Mobility Authority board meeting.
In the past CH2M has attributed delays to a number of factors, including inclement weather, unknown utilities discovered underground, hard rock and change orders—work that is beyond the original project scope—from the Mobility Authority, which oversees the MoPac project.
“The bottom line is work is progressing and change orders are ongoing,” said Dee Anne Health, the Mobility Authority’s director of external affairs and media relations. “We have no reason to be negative or concerned.”
Connecticut-based Lane Construction, which has been a subcontractor on the MoPac project since it broke ground in early 2014, will complete the rest of the project.
“Lane has seen tremendous progress on their projects,” Heath said.
Jeff Dailey, the Mobility Authority’s deputy executive director, said he has had ongoing conversations with CH2M regarding change orders and the project is progressing. He said the agency’s staffers are working with CH2M on the schedule.
“We’re really happy with what we’re seeing from Lane,” he said. “They’re working on a tough section from Enfield [Road] to [RM] 2222.”
Some weather-dependent work, however, will need to occur in late March and early April to keep the project on track, Mobility Authority officials said. This includes laying down the final pavement layer of permeable friction course on the southbound side between US 183 and RM 2222. The work will be done overnight and likely involve lane closures.
[caption id="attachment_216874" align="alignright" width="460"]
Crews worked on a retaining wall in December on the southbound side of MoPac north of Steck Avenue.[/caption]