Road projects in the city of Kyle have recently seen major progress, from closed lanes to traffic signal repairs following accidents. Check out three transportation updates from the city.
Ongoing projects
Kohlers Crossing water line project
Project: Crews will install a 24-inch water transmission line from the FM 1626 tanks on the north side of the bridge over the train tracks to the water well at the corner of Benner Road and Kohlers Crossing.
Update: The right lane of westbound traffic on Kohlers Crossing between FM 1626 and Benner Road was closed on Sept. 21. The lane closure is expected to last through December.
Timeline: August 2026-April 2027
Cost: $6,382,468.40-$7,020,715.24
Funding source: 2025 Certificates of Obligation Bonds
Kohlers Crossing and Kyle Crossing intersection signal
Project: On Sept. 26, a Texas Disposal Systems, Inc. truck struck the overhead traffic signal cable at the intersection. As a result, the traffic signal equipment and associated infrastructure must be repaired or replaced.
Update: The Kyle City Council approved a contract with Austin Traffic Signal Construction Co., LLC for the traffic signal and associated infrastructure repair.
Kohlers Crossing to Seton Parkway
Project: The project extends Kohlers Crossing to connect with Seton Parkway, with an intersection improvement at the new Kohlers extension and Bebee Road. The project also includes new pedestrian facilities, improved drainage infrastructure and new curb and gutter construction.
Update: Crews continue to work on the Kohlers-to-Seton bridge, stormwater improvements, utility relocations and roadway construction. Upcoming work includes construction of the Kohlers bridge deck and concrete rails.