Maintenance work on Rio Vista Falls, which has caused a portion of the San Marcos River to be closed since October, will continue through mid-May.
The closure runs from above the falls in Rio Vista Park and under the bridge at Cheatham Street. The $966,000 project initially was projected to be completed in March, but delays—some of which resulted from vandalism to the blue water-filled barriers used to drain the river and divert water for foundation work on the river bed—have extended the timeline of the project, said Greg Schwarz, a senior engineer with San Marcos Capital Improvements and Engineering.
He said the project, which is being completed by Austin Filter Systems Inc. Construction, might end up costing up to $100,000 over the initial amount due in part to those delays.
“On several occasions, they've been sliced overnight, and the contractor comes back, and the work area is filled with water, so he's got to patch those barriers, reset everything up and pump water out,” Schwarz said.