The city of Kyle is adjusting utilities to allow for the reconstruction of the portion of Goforth Road from I-35 to Bunton Creek Road. The road will include three lanes in some areas and four lanes in others. The city expects to award the contract for construction in March.
Timeline: March 2016-March 2017
Cost: $9.8 million
Funding sources: city of Kyle
4. Aquarena Springs Drive overpass
Temporary lane closures have begun within the project area, which includes the portion of Aquarena Springs Drive from Thorpe Lane to Charles Austin Drive in San Marcos. In early December drainage work was nearly complete. Traffic will be reduced to one lane in each direction in mid-February.