The San Marcos CISD board of trustees on Monday was presented with options for what will become of its current administration building after two air-quality tests showed parts of the building needed to be improved or renovated. Two air quality tests performed in July and September came back positive for mold. The companies that performed the tests recommended remediation be performed as soon as possible. Options presented to the board included gutting the structure, adding another story to the building, completely demolishing it or relocating it to another site.
- Option 1: $2.46 million Would involve renovating the existing building and its parking lots as well as removing the portables
- Option 2: $8.92 million Would renovate and expand the existing administration building, adding a second story to the building and providing new and renovated parking
- Option 3: $9.41 million Would demolish the entire administration building and construct a new, two-story building with new parking in its place
- Option 4: $9.29 million Would construct a new administration building and new parking on a district-owned site on Hunter Road, where the transportation, technology and food service departments are located.
- Option 5: No cost estimate Find an existing site, purchase it and renovate it as the new administration building.