Contractors leading Hill Country Village’s citywide road and drainage project said encountering a water main is among myriad reasons behind what local officials call a lack of progress.
Austin Bridge and Road began a multiphase project around the start of 2022, applying nearly $6 million in repairs and upgrades on several older streets. The project is funded by an $8.5 million bond issue passed by voters in 2019.
Brady Kosub, department manager with M&S Engineering, the city’s consulting engineering firm, addressed City Council on July 21 about residents’ complaints that work seemingly was taking longer on certain streets.
Kosub, however, said the entire project was more than 45% complete.