Check out this list of transportation projects in the San Antonio area. This list is not comprehensive. Details are subject to change.
Upcoming projects
1. Toepperwein Road from Nacogdoches Road to Raintree Forest project
- Project: Part of the 2022-27 bond program, the project will construct roadway improvements, such as sidewalks, curbs, driveway approaches and drainage, on Toepperwein Road from Nacogdoches Road to Raintree Forest.
- Update: Currently in the design phase, the project is estimated to begin in winter 2027.
- Timeline: winter 2027-fall 2028
- Cost: $14.8 million
- Funding source: 2022 general obligation bond, CPS Energy, San Antonio Water System
2. Classen Road project
- Project: Part of the 2022-27 bond program, the project will construct roadway improvements on Classen Road from Classen Spur to Knollcreek Drive. Improvements include extending the roadway, adding two lanes and a center turn lane, a sidewalk and a shared-use path, a multi-box drainage culvert and an underground drainage system.
- Update: Currently in the design phase, the project is estimated to begin this spring.
- Timeline: spring 2026-fall 2027
- Cost: $10.32 million
- Funding source: 2022 general obligation bond, San Antonio Water System
3. Evans Road drainage improvements phase 1
- Project: Part of the 2022-27 bond program, work includes rebuilding the street, widening sidewalks and improving drainage on Evans Road from Roan Park to Masonwood Drive.
- Update: According to the city documents, the project’s design phase is 70% complete.
- Timeline: summer 2025-summer 2027
- Cost: $8.45 million
- Funding source: 2022-27 bond program
Ongoing projects
4. Loop 1604 from Redland Road to Judson Road
- Project: Part of the Loop 1604 North Expansion Project, the Loop 1604 from Redland Road to Judson Road project aims to upgrade the transit corridor from a four-lane expressway to a 10-lane expressway. Additional upgrades include reconfiguring the layout of auxiliary lanes and entrance and exit ramps, and adding a high-occupancy vehicle lane in each direction.
- Update: Currently under construction, the project is Segment 5 of the larger project and is 21% complete.
- Timeline: 2025-28
- Cost: $205 million
- Funding source: state and federal funds
5. District 9 Pedestrian Mobility