Work is set to resume on the FM 1103 project in January, TxDOT Public Information Officer Tanya Brown said.

The details

Since July 2023, the FM 1103 project has been at a standstill as the Texas Department of Transportation works through conflicts with utilities and telecommunication lines.

When construction resumes, crews will begin building the sound walls along FM 1103 between I-35 and Rodeo Way, Brown said.

After the sound walls are complete, the contractor will begin road construction. An updated schedule will be provided once a start date has been confirmed.


About the project

The full project will include the expansion of FM 1103 from a two-lane road to a four-lane road with bicycle lanes and sidewalks.

The first phase from I-35 to Rodeo Way broke ground in November 2022. Cibolo City Council on May 28 authorized the city manager to sign an advance funding agreement in the amount of $3.4 million for the second phase of the project, from Rodeo Way to FM 78.