Project details
Construction on the project—which began in January 2022—is for a sanitary sewer system along Woman Hollering Creek, from the existing Sedona Lift Station to a new lift station on I-10. An additional line will be constructed to serve the Hallie’s Cove subdivision, according to the Schertz Capital Improvement Projects webpage.
The project provides initial flow of wastewater to the Cibolo Creek Municipal Authority southern water reclamation plant, according to agenda documents.
Latest update
The latest change order in the multiyear project was to correct an oversight on the project. The total expenditures on the project are not to exceed $11.2 million. Previously, an error had been made related to the installation between CPS Energy and the system, with electrical equipment not put at the correct elevation. To correct the situation, contractor Thalle Construction will construct a foundation and steel platform so an electrical conduit can be at the right elevation, according to agenda documents.
Funding for the change order is included in the city’s capital improvement plan budget and is available in the city’s wastewater capital recovery fund.
Next steps
The Woman Hollering Creek Wastewater Trunk Main and Lift Station Project is anticipated to be complete in December, according to a project sheet attached to the change order.

