Check out this list of transportation projects in the San Antonio area. This list is not comprehensive. Details are subject to change.
Upcoming
1. Vance Jackson Road (Huebner Road to Wurzbach Road) project
- Project: Part of the city of San Antonio’s 2022-2027 bond program, work includes a series of roadway improvements, such as adding a consistent two-way center turn lane, building improved sidewalks and a shared-use path, and installing underground drainage to low-water crossings. The project on Vance Jackson Road stretches from Huebner Road to Wurzbach Road.
- Update: The project is currently in the design phase and is estimated to begin construction in 2027, according to city documents.
- Timeline: winter 2027-fall 2028
- Cost: $16.4 million
- Funding source: 2022-2027 bond program
2. Bulverde Road Phase 2 project
- Project: Part of San Antonio’s 2022-27 bond program, Phase 2 will construct improvements on Bulverde Road from Green Spring Drive to Redland Road. These include new sidewalks, curbs, driveway approaches, drainage and bicycle facilities. The project will also address road wear and tear and an existing low-water crossing.
- Update: Currently in the design phase, the project will widen the road to 86 feet, expand it to four lanes, add a center turn lane, and add a sidewalk and a shared-use path, as well as drainage improvements and utility adjustments. The estimated construction start date was moved from summer 2025 to summer 2026, according to city documents.
- Timeline: summer 2026-summer 2028
- Cost: $14.6 million
- Funding sources: 2022 general obligation bond and Bexar County
Ongoing
3. Babcock Road (West Hausman to UTSA Boulevard) project
- Project: Part of San Antonio’s 2022-27 bond program, the project will widen roughly 0.4 miles of Babcock Road into a four-lane roadway with a center turn lane. The project will also add sidewalks, curbs and driveway approaches, build a mid-block pedestrian crossing and add drainage improvements.
- Update: San Antonio City Council approved a construction contract with E-Z Bel Construction LLC on Jan. 29 in an amount not to exceed $6.17 million, with $88,955 to be reimbursed by the San Antonio Water System and $241,143 to be reimbursed by CPS Energy
- Timeline: winter 2026-fall 2027
- Cost: $10 million
- Funding sources: 2022 general obligation bond, CPS Energy, San Antonio Water System and the Tree Preservation Fund
4. I-10 and Loop 1604 interchange project
- Project: Part of the Loop 1604 North Expansion Project, the Loop 1604 and I-10 interchange project will consist of eight flyover ramps, roundabouts, a high-occupancy vehicle lane and other interchange improvements, according to the Texas Department of Transportation.
- Update: TxDOT opened the eighth and final flyover ramp Feb. 5, connecting westbound Loop 1604 to westbound I-10. Known as Segment 2, the interchange is 65% done.
- Timeline: 2022-2027
- Cost: $463 million
- Funding source: state and federal funds
5. De Zavala Road project