Check out this list of transportation projects in the San Antonio area. This list is not comprehensive. Details are subject to change.

1. De Zavala Road project

Project: The De Zavala Road project will add a series of improvements, including a large pipe underneath the roadway to capture overflowing water and transport it to the Olmos Basin, raised curbs with sidewalks, dedicated bike lanes and safety buffers between bicyclists and traffic.

Update: The project is currently under construction, including the construction of two 5 ½-foot sidewalks, two 4-foot bike lanes, two 2-foot buffers, two 11-foot lanes and fresh asphalt.

Timeline: summer 2025-July 2026


Cost: $4 million

Funding source: federal grant with the remaining costs covered by 2022 bond

2. Old Fredericksburg Road project

Project: Bexar County is adding a series of improvements to Old Fredericksburg Road in a five-phase project, stretching 1.7 miles from I-10 to FM 3351. The project includes five drainage improvements, a new bridge at a low-water crossing, a roundabout at Lost Creek Gap and the addition of turn lanes at multiple intersections. Other improvements include adding paved shoulders, sidewalk improvements and other multimodal transportation improvements, as well as relocating utilities.


Update: According to county documents, the project is currently under construction, with 30% of Phase I completed, which includes bridge construction and culvert construction at the existing roundabout at Woodland Green, Millstone Cove and Old Fredericksburg Road.

Timeline: January 2025-May 2027

Cost: $13.252 million

Funding source: Bexar County, San Antonio Water System and the city of Fair Oaks Ranch water


3. Evans Road Corridor project

Project: The Evans Road Corridor Project will stretch from Peacemaker to Barbara Bush Middle School and will include two new traffic signals, asphalt milling, overlay work, sidewalks, curb ramps, driveway approaches, a signalized pedestrian crossing and median modifications.

Update: The project was awarded to E-Z Bel Construction LLC during the Sept. 11 San Antonio City Council meeting.

Timeline: fall 2025-summer 2027.


Cost: $1.447 million

Funding source: 2022-2027 bond program

4. District 9 Pedestrian Mobility project

Project: Part of the city of San Antonio’s 2022-27 bond program, the project seeks to widen pedestrian access. The project includes the construction of turn lanes, new sidewalks, driveway approaches and drainage improvements in the Stone Oak area.


Update: Currently in the design phase, associated projects for District 9 include constructing intersection improvements at Stone Oak Parkway and Evans Road and at Stone Oak Parkway and Hardy Oak Boulevard.

Timeline: summer 2025-summer 2027

Cost: $5.066 million

Funding source: 2022 General Obligation Bond

5. Vance Jackson Road (Huebner Road to Wurzbach Road) project

Project: Part of the city of San Antonio’s 2022-2027 bond program, work includes a series of roadway improvements, such as adding a consistent two-way center turn lane, building improved sidewalks and a shared-use path and installing underground drainage to low-water crossings. The project on Vance Jackson Road stretches from Huebner Road to Wurzbach Road.

Update: The project is currently in the design phase and is estimated to begin construction in 2027

Timeline: winter 2027-fall 2028

Cost: $16.401 million

Funding source: 2022-2027 bond program