As part of the Loop 1604 North Expansion project, the Texas Department of Transportation will close a series of roadways for construction.

What you need to know

According to the TxDOT Loop 1604 North Expansion webpage, closures will occur during the week and will not affect weekend travel.

Weekday lane closures
  • Alternating lanes on Loop 1604 eastbound frontage road from Bandera Road to I-10 will be closed from 9 a.m.-3 p.m. Jan. 27-Feb. 3 for traffic barrier, sidewalk construction and beam placement/bridge construction. Lane closures will alternate daily.
  • Alternating lanes of westbound Loop 1604 frontage road from I-10 to Bandera Road will be closed from 9 a.m.-3 p.m. Jan. 27-Feb. 3 for traffic barrier, sidewalk construction and beam placement/bridge construction. Lane closures will alternate daily.
  • The Loop 1604 turnarounds at Hausman Road will be closed from 9 a.m.-3 p.m. Jan. 27-Feb. 3 for bridge widening. Only one turnaround will be closed at a time.
  • The Loop 1604 turnarounds at Kyle Seale Parkway will be closed from 9 a.m.-3 p.m. Jan. 27-Feb. 3 for bridge widening. Only one turnaround will be closed at a time.
  • The Loop 1604 turnaround at La Cantera Parkway/John Peace Boulevard will be closed from 9 a.m.-3 p.m. Jan. 27-Feb. 3 for bridge widening. Only one turnaround will be closed at a time.
Loop 1604 and I-10 interchange weeknight closures
  • The Loop 1604 westbound frontage road right turn to I-10 westbound will be closed from 9 p.m.-5 a.m. Jan. 27-Feb. 3 for bridge construction.
  • The I-10 eastbound frontage road from Loop 1604 interchange to UTSA Boulevard will be closed from 9 p.m.-5 a.m. Jan. 27-Feb. 3 for bridge construction.
  • Eastbound Loop 1604 main lanes will be closed from La Cantera Parkway to Vance Jackson Road from 9 p.m.-5 a.m. Jan. 27-Feb. 3 for bridge construction.
  • Westbound Loop 1604 main lanes from Vance Jackson to La Cantera Parkway will be closed from 9 p.m.-5 a.m. Jan. 27-Feb. 3 for bridge construction.
  • Eastbound I-10 main lanes from La Cantera Parkway to UTSA Boulevard will be closed from 9 p.m.-5 a.m. Jan. 27-Feb. 3 for bridge construction.
  • Westbound I-10 main lanes from UTSA Boulevard to La Cantera Parkway will be closed from 9 p.m.-5 a.m. Jan. 27-Feb. 3 for bridge construction.
  • The eastbound I-10 frontage road at the Loop 1604 interchange will be closed from 9 p.m.-5 a.m. Jan. 27-Feb. 3 for bridge construction.
  • The westbound I-10 frontage road at the Loop 1604 interchange will be closed from 9 p.m.-5 a.m. Jan. 27-Feb. 3 for bridge construction.
  • The eastbound I-10 main lane exit ramp to Loop 1604 westbound will be closed from 9 p.m.-5 a.m. Jan. 27-Feb. 3 for bridge construction.
  • The ramp/cloverleaf from westbound I-10 to Loop 1604 westbound will be closed from 9 p.m.-5 a.m. Jan. 27-Feb. 3 for bridge construction.
  • The westbound Loop 1604 bypass lane at the I-10 interchange will be closed from 9 p.m.-5 a.m. Jan. 27-Feb. 3 for bridge construction.
  • The westbound I-10 frontage road from the Loop 1604 interchange to La Cantera Parkway will be closed from 9 p.m.-5 a.m. Jan. 27-Feb. 3 for bridge construction.
  • The westbound I-10 frontage road from the Loop 1604 interchange to La Cantera Parkway will be closed from 9 p.m.-5 a.m. for bridge construction.
  • The I-10 westbound exit ramp to La Cantera Parkway will be closed from 10:30 p.m.-5 a.m. Jan. 27-Feb. 3 for bridge construction.
For more information on road closures, visit TxDOT’s Loop 1604 North Expansion webpage.