A cave formation discovered in South Williamson County during a road construction project was filled and sealed off in late October after county and state officials determined leaving it intact could present an environmental hazard.
On June 13 construction crews unearthed the entrance to the cave while excavating earth for a storm sewer drain adjacent to the ongoing RM 620 road widening project. Per state law, construction near the discovery immediately halted so that officials from Williamson County, the Texas Department of Transportation and the Texas Commission on Environmental Quality could assess the cave and devise a plan of what to do next.
Following more than two months of geological and hydrological review, TxDOT submitted a recommendation to the TCEQ on Aug. 23 that the cave be filled in order to prevent future contamination of the Edwards Aquifer—the vast underground natural well system that provides an estimated 1.7 million Texans with water.
"Based on a review of the options presented by TxDOT, TCEQ agreed that filling the [cave] with concrete but leaving the bottom porous and permeable with gravel/rocks was the safest and most protective option," the TCEQ noted in an official statement. "Written approval was issued on Sept. 13, 2013, to TXDOT."