The Richardson ISD board of trustees approved the final stage for the J.J. Pearce High School renovation and expansion project.
The board of trustees approved a guaranteed maximum price of just over $99 million for the third phase of construction during its May 9 meeting. Phase 3 of the project will consist of renovating existing classroom spaces, reconfiguring existing spaces and further upgrades to existing systems/infrastructure, according documents prepared for the board.
Two previous renovation phases were approved in 2021. The first phase of construction, which included the construction of a new turf softball field, the installation of new turf on the existing baseball field and the construction of additional campus parking spaces, was approved by the RISD board for a guaranteed maximum price of just over $6 million during a June 7 meeting, according to district officials.
The second phase of renovations, which included upgrades to existing systems/infrastructure and adding new building additions to increase campus capacity, was approved for a guaranteed maximum price of just over $17 million on Aug. 9. The second phase of construction was further approved by Richardson City Council during an Oct. 18 meeting.