Here are 10 road projects upcoming or ongoing in Prosper and Celina, according to each entity's capital improvement website. This list is not comprehensive.
Upcoming
Coleman Street updates
Project: Coleman Street will be updated from Prosper Trail to Prosper High School. The project will create a four-lane divided roadway.
Update: The project is in the design phase with construction estimated to start in the winter.
Craig Road construction
Project: The project will update Craig Road from Preston Road to Fifth Street. The project will include paving and drainage.
Update: The project is in the pre-construction phase with construction expected to start this fall.
Frontier Parkway updates
Project: The Texas Department of Transportation will spearhead a reconstruction of the existing asphalt roadway to four lanes from Preston Road to Custer Road.
Update: TxDOT is waiting on funding to start construction.
Ongoing
First Street widening
Project: First Street is being widened from a two-lane roadway to a four-lane divided roadway from Dallas North Tollway to Coleman Street. The project includes concrete curbs, underground drainage improvements and a water line.
Update: The project is under construction.
Coit Road construction
Project: Coit Road will be updated to a four-lane roadway, which will eventually become a six-lane roadway. The project spans Coit Road from Prosper Trail to First Street.
Update: The project is under construction and is expected to be completed later this year.
Legacy Drive improvements
Project: Legacy Drive is being updated from Prosper Trail to Parvin Road. The improvements include the construction of two additional lanes of Legacy Drive with two median openings and left turn lanes.
Update: The project is under construction with completion expected next summer.
Choate Parkway construction
Project: Choate Parkway will be reconstructed to a two-lane divided roadway. Drainage, signage and pavement markings will be included in the project. The project is shared with the city and the adjacent subdivision.
Update: The project is under construction.
Coit Road improvements
Project: Coit Road will be reconstructed from a two-lane asphalt roadway to a four-lane divided roadway. The project spans Vest Lane to Choate Parkway. The project is shared between the city of Celina and Collin County.
Update: The project is under construction and on track.
Hillside Drive concrete replacement
Project: The concrete will be removed and replaced on Hillside Drive.
Update: The project is under construction and is about 40% completed.
Oklahoma Drive construction
Project: Oklahoma Drive will be replaced from Pecan Street to Malone Drive. The project will replace existing asphalt and construct two new concrete lanes.
Update: The project is under construction.