Check out 9 upcoming and ongoing transportation projects in Prosper and Celina.
This list is not comprehensive.
Upcoming projects
1. Teel Parkway construction

Local · Trusted · Free
The Morning Impact — your neighborhood's most important stories, delivered every morning.


Check out 9 upcoming and ongoing transportation projects in Prosper and Celina.
This list is not comprehensive.
Upcoming projects
1. Teel Parkway construction
Project: Teel Parkway will be updated with new pavement into a four-lane concrete roadway from First Street to Freeman Way.
Update: The project is in the design phase with the project expected to start next winter.
Project: Prosper Trail will undergo a full pavement reconstruction from Coit Road to Custer Road. The new pavement section will be a four-lane concrete divided roadway.
Update: The design phase is nearing completion, and construction is expected to begin in summer 2028.
Project: Frontier Parkway will be reconstructed to a four-lane concrete roadway from Preston Road to Custer Road.
Update: The project is in the design phase with 60% of the plans sent to the Texas Department of Transportation. Construction is slated to begin in 2027 based on available funding.
4. FM 428 improvements
Project: FM 428 is undergoing rehabilitation and maintenance from FM 455 to the Denton County line, including asphalt removal and replacement.
Update: Crews are working on connections to side streets, utility improvements and roadway striping as the project wraps up.
Project: Coit Road will be widened from a four-lane roadway to a six-lane concrete roadway from First Street to Prosper Trail. The project includes the roadway, curbs, underground work and drainage.
Update: Construction is roughly two-thirds complete. Paving was scheduled to begin in early June but has been delayed due to heavy rain.
Project: CR 52 is being reconstructed from West Outer Loop to FM 428. The project will add an asphalt overlay and underground drainage upgrades.
Update: Construction has entered Phase 3. During this phase, residents will use West Outer Loop while FM 428 is reserved for hospital delivery vehicles, according to the city’s social media.
Project: Coit Road will receive an asphalt overlay from CR 92 to Ousley Boulevard and from Lynn Stambaugh Parkway to J. Fred Smith Parkway.
Update: Construction on the first section from CR 92 to Ousley Boulevard started on June 17.
Project: Choate Parkway is being reconstructed from the existing two-lane roadway to a six-lane divided roadway from Coit Road to Roseland Parkway.
Update: The project is divided into two phases. The first phase is under construction, and the second phase has been delayed due to utility relocation.
Project: First Street will be widened from a two-lane rural roadway to a four-lane divided suburban roadway from Dallas North Tollway to Coleman Street.
Update: Contractors began work in May and are installing waterlines. The town is coordinating with BNSF Railway to widen the rail crossing with temporary gates and pavement while construction is underway.