Here are 10 road projects in Prosper and Celina.
Upcoming
FM 1385 reconstruction
Project: The FM 1385 reconstruction project includes the widening of the nearly 12 miles on FM 1385 from US 380 to FM 455 in Denton County. The existing roadway is two lanes. The proposed widening will increase the roadway to a six-lane divided urban roadway.
Update: The project is in the design phase and is being led by the Texas Department of Transportation.
Timeline: TBD
Cost: $189 million
Funding source: TxDOT
Teel Parkway construction
Project: Teel Parkway will be updated from First Street to Freeman Way. The updates will include new pavement and widening to a four-lane concrete roadway.
Update: The project is in the design phase.
Prosper Trail updates
Project: Prosper Trail will be reconstructed with new pavement, including replacement of the bridge at Wilson Creek Crossing. The new pavement, which will span Coit Road to Custer Road, will be a four-lane divided roadway.
Update: The project is in the design phase with construction expected to start in 2028.
Frontier Parkway improvements
Project: TxDOT will be reconstructing the existing asphalt roadway to a four-lane concrete road. The project will include underground drainage and sidewalks from Preston Road to Custer Road.
Update: The project is in the design phase. TxDOT is waiting on funding to start the project and a timeline has not been provided.
Timeline: TBD
Cost: TBD
Funding source: TBD
Pecan, Illinois street updates
Project: The project will reconstruct the portion of Pecan Street from Arizona Drive to Florida Drive. This design also includes the full depth reclamation/replacement of the asphalt pavement of Arizona Drive from Pecan Street to Beech Street, and Illinois Street from Walnut Street to Beech Street.
Update: The project is in the design phase.
Ongoing
First Street widening
Project: First Street will be widened from a two-lane rural roadway to a four-lane divided suburban roadway. The project spans First Street from the Dallas North Tollway to Coleman Street.
Update: The project is under construction.
Dallas North Tollway construction
Project: The North Texas Tollway Authority is constructing a six-lane divided highway from US 380 to FM 428. The project will construct several overpasses at key intersections that span the future roadway.
Update: The project is under construction.
Coit Road construction
Project: Coit Road will be constructed to a four-lane roadway of an ultimate six-lane roadway. The project will include concrete, curb, gutters and underground drainage. It will span from First Street to Prosper Trail.
Update: The project is under construction and expected to wrap later this year or early next year.
Choate Parkway improvements
Project: The project consists of reconstructing the existing road from a two-lane roadway to a six-lane divided roadway. The project spans from Coit Road to Roseland Parkway. Lighting and landscaping will not be included in the project. This project will be a shared project between the city and the adjacent subdivision developer.
Update: The project is under construction and about 70% completed though it has seen some disruptions.
Coit Road improvements
Project: Coit Road is being reconstructed from an existing two-lane asphalt roadway to a four-lane divided primary roadway. The project spans from Vest Lane to Choate Parkway.
Update: The project is under construction.